Larsen & Toubro Ltd. (Realty Division)

9 RERA-registered projects in Maharashtra

9
projects
1,460
total units
4
delayed (avg 829d)

Developer overview

  • Larsen & Toubro Ltd. (Realty Division) has 9 RERA-registered projects with a total of 1,460 units, of which 1,081 are sold.
  • 4 projects are delayed, with an average delay of 829 days.
  • 30 litigation cases on record.
  • 4 projects have received extension certificates.

Track record

Active
5
In Extension
4

Active districts

Mumbai Suburban (9)