ActivePR1260002501967Registered Jan 20260 red flags in 9 checks

Yashodha East Rise

A residential / group housing project by Yashodha Reality in WAGHOLI, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
8%
cost-weighted
Declared completion
Dec 2028
no delay on record
Units sold
0 / 92
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Yashodha Reality · Partnership
Project type
Residential / Group Housing
Land area
3,632 m² · Permissible built-up (FSI) 6,521 m²
Total units
92 across 2 wings
Estimated cost
₹38.1 Cr
Parking
81 four-wheeler · 0 two-wheeler
Application date
05 Dec 2025
Buildings & units

WING - A & WING - B

Floors and unit counts as filed.

WingFloors sanctionedTotal units
WING - A12 of 12 proposed74
WING - B3 of 3 proposed18
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/2008/41887
Structural engineer
Project bank
HDFC BANK
Location

Where it sits

WAGHOLI, Pune — 412207.

Locality
WAGHOLI
District
Pune
Authority
Pune Metropolitan Region Development Authority
Red flags

0 red flags in 9 checks

The full report shows what each check looked at in this project's record. Absence of a flag reflects the record as filed, not an assessment of safety.

  • Registration status3 checks, none raised
  • Complaints & recovery warrants2 checks, none raised
  • Litigation & encumbrance disclosure2 checks, none raised
  • Sales & cost filings2 checks, none raised
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

1
commencement certificate on file
3
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99

Yashodha East Rise: common questions

Is Yashodha East Rise RERA registered?

Yes. Yashodha East Rise is registered with MahaRERA under registration number PR1260002501967, granted on 1 January 2026. As of July 2026, the registration is active.

What is the possession date of Yashodha East Rise?

The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Yashodha East Rise?

Yashodha East Rise is developed by Yashodha Reality, the promoter named in its MahaRERA registration.

Where is Yashodha East Rise located?

Yashodha East Rise is in Wagholi, Pune (PIN 412207), Maharashtra, as declared in its RERA registration.

How many units does Yashodha East Rise have, and how many are sold?

Yashodha East Rise has 92 units on its RERA registration. 0 were reported sold as of July 2026, leaving 92 unsold.

How much construction of Yashodha East Rise is complete?

By the developer's own quarterly filing, 8% of the work is done, measured against the project's cost estimate.

Is there any litigation against Yashodha East Rise?

No litigation is declared on Yashodha East Rise's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.