Status & progress

Per MahaRERA record as of Jul 2026.

Construction
29%
cost-weighted
Declared completion
Dec 2027
no delay on record
Units sold
33 / 124
27% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Dhyan Projects Private Limited · Company
Project type
Residential / Group Housing
Land area
1,929 m² · Permissible built-up (FSI) 17,719 m²
Total units
124 across 2 wings
Estimated cost
₹198.5 Cr
Land ownership
Promoter is the landowner
Parking
204 four-wheeler · 0 two-wheeler
Held outside open sale
33 rehab
Application date
10 Aug 2024
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA22 of 22 proposed62
NA22 of 22 proposed62
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ELLORA PROJECT CONSULTANTS PVT LTD · D/294/LS
Structural engineer
· LS:840017667
Project bank
INDIAN BANK
Location

Where it sits

VILE PARLE, Mumbai Suburban — 400049.

Locality
VILE PARLE
District
Mumbai Suburban
Authority
Building Permission Cell, Greater Mumbai / MHADA
Red flags

0 red flags in 9 checks

The full report shows what each check looked at in this project's record. Absence of a flag reflects the record as filed, not an assessment of safety.

  • Registration status3 checks, none raised
  • Complaints & recovery warrants2 checks, none raised
  • Litigation & encumbrance disclosure2 checks, none raised
  • Sales & cost filings2 checks, none raised
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

3
commencement certificates on file
1
landowner on record
11
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99
Legal & encumbrance

Litigation & charges

1
court case on record

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

The Arcadian: common questions

Is The Arcadian RERA registered?

Yes. The Arcadian is registered with MahaRERA under registration number P51800077876, granted on 7 November 2024. As of July 2026, the registration is active.

What is the possession date of The Arcadian?

The developer has declared completion by December 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of The Arcadian?

The Arcadian is developed by Dhyan Projects Private Limited, the promoter named in its MahaRERA registration.

Where is The Arcadian located?

The Arcadian is in Vile Parle, Mumbai (PIN 400049), Maharashtra, as declared in its RERA registration.

How many units does The Arcadian have, and how many are sold?

The Arcadian has 124 units on its RERA registration. 37 were reported sold as of July 2026, leaving 87 unsold.

How much construction of The Arcadian is complete?

By the developer's own quarterly filing, 29% of the work is done, measured against the project's cost estimate.

Is there any litigation against The Arcadian?

1 litigation case is declared on The Arcadian's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Vile Parle

All RERA projects in Vile Parle →