ActivePM1330002500422Registered Jul 20250 red flags in 9 checks

Sai Castle

A mixed project by Pinnakle Lifespaces LLP in JOVELI, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
26%
cost-weighted
Declared completion
Dec 2028
no delay on record
Units sold
6 / 129
5% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Pinnakle Lifespaces LLP · Limited Liability Partnership
Project type
Mixed
Land area
3,420 m² · Permissible built-up (FSI) 6,221 m²
Total units
129 across 2 wings
Estimated cost
₹16.3 Cr
Land ownership
Promoter is the landowner
Parking
21 four-wheeler · 146 two-wheeler
Held outside open sale
14 landowner/investor share
Application date
11 Jun 2025
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA12 of 12 proposed124
NA3 of 3 proposed5
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
SPACE DESIGNERSS · CA/2022/154045
Structural engineer
ATUL KUDTARKAR AND ASSOCIATES PVT LTD · STATE/R/2025/APL/16827
Project bank
HDFC BANK
Location

Where it sits

JOVELI, Thane — 421503.

Locality
JOVELI
District
Thane
Authority
Kulgoan Badlapur Municipal Council
Red flags

0 red flags in 9 checks

The full report shows what each check looked at in this project's record. Absence of a flag reflects the record as filed, not an assessment of safety.

  • Registration status3 checks, none raised
  • Complaints & recovery warrants2 checks, none raised
  • Litigation & encumbrance disclosure2 checks, none raised
  • Sales & cost filings2 checks, none raised
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

1
commencement certificate on file
5
landowners on record
3
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99

Sai Castle: common questions

Is Sai Castle RERA registered?

Yes. Sai Castle is registered with MahaRERA under registration number PM1330002500422, granted on 29 July 2025. As of July 2026, the registration is active.

What is the possession date of Sai Castle?

The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Sai Castle?

Sai Castle is developed by Pinnakle Lifespaces LLP, the promoter named in its MahaRERA registration.

Where is Sai Castle located?

Sai Castle is in Joveli, Thane (PIN 421503), Maharashtra, as declared in its RERA registration.

How many units does Sai Castle have, and how many are sold?

Sai Castle has 129 units on its RERA registration. 12 were reported sold as of July 2026, leaving 117 unsold.

How much construction of Sai Castle is complete?

By the developer's own quarterly filing, 26% of the work is done, measured against the project's cost estimate.

Is there any litigation against Sai Castle?

No litigation is declared on Sai Castle's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.