Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Aethon Developers Private Limited · Company
- Project type
- Residential / Group Housing
- Land area
- 7,527 m² · Permissible built-up (FSI) 42,372 m²
- Total units
- 193 across 1 wing
- Estimated cost
- ₹0 Cr
- Parking
- 244 four-wheeler · 0 two-wheeler
- Application date
- 05 Apr 2025
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 51 of 51 proposed | 193 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- Ninad Dinkar Mhaskar · CA/2001/28533
- Structural engineer
- Sanjay Singh
- Project bank
- STANDARD CHARTERED BANK
Where it sits
LOWER PAREL, Mumbai City — 400013.
0 red flags in 9 checks
The full report shows what each check looked at in this project's record. Absence of a flag reflects the record as filed, not an assessment of safety.
- Registration status3 checks, none raised
- Complaints & recovery warrants2 checks, none raised
- Litigation & encumbrance disclosure2 checks, none raised
- Sales & cost filings2 checks, none raised
What to verify before you pay a booking amount
Questions for the promoter and documents to ask for, each drawn from this project's record.
Unlock the checklist for this project, with the record entry behind each step.
Unlock full report — ₹99Litigation & charges
Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.
Unlock full report — ₹99Runwal Raaya - Tower 1: common questions
Is Runwal Raaya - Tower 1 RERA registered?
Yes. Runwal Raaya - Tower 1 is registered with MahaRERA under registration number P51900080252, granted on 15 May 2025. As of July 2026, the registration is active.
What is the possession date of Runwal Raaya - Tower 1?
The developer has declared completion by December 2032 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Runwal Raaya - Tower 1?
Runwal Raaya - Tower 1 is developed by Aethon Developers Private Limited, the promoter named in its MahaRERA registration.
Where is Runwal Raaya - Tower 1 located?
Runwal Raaya - Tower 1 is in Lower Parel, Mumbai (PIN 400013), Maharashtra, as declared in its RERA registration.
How many units does Runwal Raaya - Tower 1 have, and how many are sold?
Runwal Raaya - Tower 1 has 193 units on its RERA registration. 36 were reported sold as of July 2026, leaving 157 unsold.
How much construction of Runwal Raaya - Tower 1 is complete?
By the developer's own quarterly filing, 11% of the work is done, measured against the project's cost estimate.
Is there any litigation against Runwal Raaya - Tower 1?
2 litigation cases are declared on Runwal Raaya - Tower 1's MahaRERA record. The full report lists each case with its court and status.
More RERA projects in Lower Parel
- 7 Mahalaxmi - Tower 3 · Mumbai City
- Sila Tower · Mumbai City
- Embassy Citadel · Mumbai City
- 7 Mahalaxmi - Tower 1 · Mumbai City
- Adi Darsshan · Mumbai City
- Raheja Imperia II · Mumbai City
- Minerva · Mumbai City
- Arihant Towers - by MJ Shah · Mumbai City
Other projects by Aethon Developers Private Limited
- Runwal Raaya - Tower 2 · Mumbai City