ActivePM1330002501154Registered Oct 20250 red flags in 9 checks

Patels Elara

A mixed project by Apace Realty in PALE, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
29%
cost-weighted
Declared completion
Nov 2028
no delay on record
Units sold
7 / 59
12% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Apace Realty · Partnership
Project type
Mixed
Land area
1,363 m² · Permissible built-up (FSI) 4,663 m²
Total units
59 across 1 wing
Estimated cost
₹14 Cr
Parking
18 four-wheeler · 60 two-wheeler
Application date
14 Aug 2025
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA13 of 13 proposed59
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/2024/174800
Structural engineer
Project bank
ICICI BANK LIMITED
Location

Where it sits

PALE, Thane — 421501.

Locality
PALE
District
Thane
Authority
AMBERNATH MUNCIPAL COUNCIL
Red flags

0 red flags in 9 checks

The full report shows what each check looked at in this project's record. Absence of a flag reflects the record as filed, not an assessment of safety.

  • Registration status3 checks, none raised
  • Complaints & recovery warrants2 checks, none raised
  • Litigation & encumbrance disclosure2 checks, none raised
  • Sales & cost filings2 checks, none raised
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

1
commencement certificate on file
4
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99

Patels Elara: common questions

Is Patels Elara RERA registered?

Yes. Patels Elara is registered with MahaRERA under registration number PM1330002501154, granted on 9 October 2025. As of July 2026, the registration is active.

What is the possession date of Patels Elara?

The developer has declared completion by November 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Patels Elara?

Patels Elara is developed by Apace Realty, the promoter named in its MahaRERA registration.

Where is Patels Elara located?

Patels Elara is in Pale, Thane (PIN 421501), Maharashtra, as declared in its RERA registration.

How many units does Patels Elara have, and how many are sold?

Patels Elara has 59 units on its RERA registration. 12 were reported sold as of July 2026, leaving 47 unsold.

How much construction of Patels Elara is complete?

By the developer's own quarterly filing, 29% of the work is done, measured against the project's cost estimate.

Is there any litigation against Patels Elara?

No litigation is declared on Patels Elara's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Pale

All RERA projects in Pale →