In ExtensionP51800011901Registered Aug 2017Delayed 2832dExtension1 red flag

Mayur Tower

A residential / group housing project by Geopreneur Spire Realty in Khernagar, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
65%
cost-weighted
Declared completion
Dec 2026
delayed 2832d
Units sold
18 / 127
14% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Geopreneur Spire Realty · Partnership
Project type
Residential / Group Housing
Land area
1,834 m² · Permissible built-up (FSI) 8,221 m²
Total units
127 across 2 wings
Estimated cost
₹128.4 Cr
Land ownership
Promoter is the landowner
Held outside open sale
59 rehab
Application date
31 Jul 2017
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA19 of 19 proposed59
NA19 of 19 proposed68
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
HARISH GANDHI
Structural engineer
· CA/12660
Project bank
HDFC BANK
Location

Where it sits

Khernagar, Mumbai Suburban — 400051.

Locality
Khernagar
District
Mumbai Suburban
Authority
MHADA
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

3
commencement certificates on file
1
landowner on record
4
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Mar 2019
completion first declared
Dec 2026
completion proposed now
2832 days
later than first declared

Unlock the delay analysis and the sales & construction narrative for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

10
MahaRERA complaints filed
5
complaints with non-compliance applied
4
court cases on record

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Mayur Tower: common questions

Is Mayur Tower RERA registered?

Yes. Mayur Tower is registered with MahaRERA under registration number P51800011901, granted on 31 August 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Mayur Tower?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original March 2019. The record shows the project running 2832 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Mayur Tower?

Mayur Tower is developed by Geopreneur Spire Realty, the promoter named in its MahaRERA registration.

Where is Mayur Tower located?

Mayur Tower is in Khernagar, Mumbai (PIN 400051), Maharashtra, as declared in its RERA registration.

How many units does Mayur Tower have, and how many are sold?

Mayur Tower has 127 units on its RERA registration. 52 were reported sold as of September 2026, leaving 75 unsold.

How much construction of Mayur Tower is complete?

By the developer's own quarterly filing, 65% of the work is done, measured against the project's cost estimate.

Is there any litigation against Mayur Tower?

4 litigation cases are declared on Mayur Tower's MahaRERA record. The full report lists each case with its court and status.