In ExtensionP51800012210Registered Sept 2017Delayed 639dExtension1 red flag

Mass Metropolis

A others project by Grace Urban Development Corporation in CHEMBUR, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
89%
cost-weighted
Declared completion
Sept 2026
delayed 639d
Units sold
244 / 467
52% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Grace Urban Development Corporation · Partnership
Project type
Others
Land area
10,030 m² · Permissible built-up (FSI) 27,597 m²
Total units
467 across 1 wing
Estimated cost
₹128.4 Cr
Land ownership
Promoter is the landowner
Parking
132 four-wheeler · 0 two-wheeler
Held outside open sale
20 landowner/investor share · 11 reserved
Application date
10 Aug 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA19 of 19 proposed467
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
VIEW DIMENSION · CA/2015/68168
Structural engineer
· S/811/S.S
Project bank
KOTAK MAHINDRA BANK LIMITED
Location

Where it sits

CHEMBUR, Mumbai Suburban — 400071.

Locality
CHEMBUR
District
Mumbai Suburban
Authority
SLUM REHABILITATION AUTHORITY
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

3
commencement certificates on file
1
landowner on record
4
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Dec 2024
completion first declared
Sept 2026
completion proposed now
639 days
later than first declared

Unlock the delay analysis and the sales & construction narrative for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

17
MahaRERA complaints filed
4
complaints with non-compliance applied
2
court cases on record

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Mass Metropolis: common questions

Is Mass Metropolis RERA registered?

Yes. Mass Metropolis is registered with MahaRERA under registration number P51800012210, granted on 1 September 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Mass Metropolis?

The developer has declared completion by September 2026 in its MahaRERA filing, revised from the original December 2024. The record shows the project running 639 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Mass Metropolis?

Mass Metropolis is developed by Grace Urban Development Corporation, the promoter named in its MahaRERA registration.

Where is Mass Metropolis located?

Mass Metropolis is in Chembur, Mumbai (PIN 400071), Maharashtra, as declared in its RERA registration.

How many units does Mass Metropolis have, and how many are sold?

Mass Metropolis has 467 units on its RERA registration. 291 were reported sold as of September 2026, leaving 176 unsold.

How much construction of Mass Metropolis is complete?

By the developer's own quarterly filing, 89% of the work is done, measured against the project's cost estimate.

Is there any litigation against Mass Metropolis?

2 litigation cases are declared on Mass Metropolis's MahaRERA record. The full report lists each case with its court and status.