In ExtensionP51700048647Registered Jan 2023Delayed 365dExtension0 red flags in 9 checks

Dev Ellanza

A others project by DLS Enterprises in TITWALA, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
55%
cost-weighted
Declared completion
Apr 2027
delayed 365d
Units sold
16 / 117
14% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
DLS Enterprises · Partnership
Project type
Others
Land area
2,500 m² · Permissible built-up (FSI) 7,881 m²
Total units
117 across 1 wing
Estimated cost
₹20.3 Cr
Parking
185 four-wheeler · 18 two-wheeler
Application date
23 Oct 2022
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA15 of 15 proposed117
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
VIJAY PANDEY & ASSOCIATES · CA/96/20081
Structural engineer
Ram V Marathe · STATE/R/2024/APL/09587
Project bank
HDFC BANK
Location

Where it sits

TITWALA, Thane — 421605.

Locality
TITWALA
District
Thane
Authority
Kalyan Dombivali Municipal Corporation
Red flags

0 red flags in 9 checks

The full report shows what each check looked at in this project's record. Absence of a flag reflects the record as filed, not an assessment of safety.

  • Registration status3 checks, none raised
  • Complaints & recovery warrants2 checks, none raised
  • Litigation & encumbrance disclosure2 checks, none raised
  • Sales & cost filings2 checks, none raised
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

2
commencement certificates on file
5
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99

Dev Ellanza: common questions

Is Dev Ellanza RERA registered?

Yes. Dev Ellanza is registered with MahaRERA under registration number P51700048647, granted on 10 January 2023. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Dev Ellanza?

The developer has declared completion by April 2027 in its MahaRERA filing, revised from the original April 2026. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Dev Ellanza?

Dev Ellanza is developed by DLS Enterprises, the promoter named in its MahaRERA registration.

Where is Dev Ellanza located?

Dev Ellanza is in Titwala, Thane (PIN 421605), Maharashtra, as declared in its RERA registration.

How many units does Dev Ellanza have, and how many are sold?

Dev Ellanza has 117 units on its RERA registration. 32 were reported sold as of July 2026, leaving 85 unsold.

How much construction of Dev Ellanza is complete?

By the developer's own quarterly filing, 55% of the work is done, measured against the project's cost estimate.

Is there any litigation against Dev Ellanza?

No litigation is declared on Dev Ellanza's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.