In ExtensionP51800032085Registered Dec 2021Delayed 1095dExtension1 red flag

Asmi Legend

A others project by Angel Construction Company in Laxmi Nagar Goregaon West, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
84%
cost-weighted
Declared completion
Dec 2027
delayed 1095d
Units sold
95 / 168
57% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Angel Construction Company · Partnership
Project type
Others
Land area
3,077 m² · Permissible built-up (FSI) 7,142 m²
Total units
168 across 3 wings
Estimated cost
₹40 Cr
Application date
18 Oct 2021
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA4 of 4 proposed6
NA20 of 20 proposed77
NA21 of 21 proposed85
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
VASTU KHUBI · K/280/LS
Structural engineer
SURA AND ASSOCIATES · 840002656
Project bank
HDFC BANK
Location

Where it sits

Laxmi Nagar Goregaon West, Mumbai Suburban — 400104.

Locality
Laxmi Nagar Goregaon West
District
Mumbai Suburban
Authority
MUNICIPAL CORPORATION OF GREATER MUMBAI
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
What to verify

What to verify before you pay a booking amount

Questions for the promoter and documents to ask for, each drawn from this project's record.

4
commencement certificates on file
3
professionals declared

Unlock the checklist for this project, with the record entry behind each step.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Dec 2024
completion first declared
Dec 2027
completion proposed now
1095 days
later than first declared

Unlock the delay analysis and the sales & construction narrative for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

3
MahaRERA complaints filed
6
court cases on record
Yes
encumbrance on record

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Asmi Legend: common questions

Is Asmi Legend RERA registered?

Yes. Asmi Legend is registered with MahaRERA under registration number P51800032085, granted on 6 December 2021. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Asmi Legend?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2024. The record shows the project running 1095 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Asmi Legend?

Asmi Legend is developed by Angel Construction Company, the promoter named in its MahaRERA registration.

Where is Asmi Legend located?

Asmi Legend is in Mumbai (PIN 400104), Maharashtra, as declared in its RERA registration.

How many units does Asmi Legend have, and how many are sold?

Asmi Legend has 168 units on its RERA registration. 99 were reported sold as of September 2026, leaving 69 unsold.

How much construction of Asmi Legend is complete?

By the developer's own quarterly filing, 84% of the work is done, measured against the project's cost estimate.

Is there any litigation against Asmi Legend?

6 litigation cases are declared on Asmi Legend's MahaRERA record. The full report lists each case with its court and status.